- Report Date
- December 2019
Achievements this Period
- Build
- The cross reference file to convert individual's staff id to uun has been prepared
- Single Sign On has been successfully configured
- Data Transfer
- Work is on-going to investigate the suppliers preferred option of data encryption of PGP
- Information Security have approved the proposed method of data transfer
- Confirmation to use visitor data has been confirmed by Student Services
Issues
Next Steps
- Build Phase
- Complete PGP encryption
- Complete preparation of the Test environment
- User Acceptance Testing
- Arrange for user id's to be updated from staff id to uun
- Commence User Acceptance testing
- Go-Live Preparations
- Commence go-live preparations with regards to
- completion of System definition Document
- completion of Technical Architecture Document
- completion of deployment check lists
- Approved budget
- 58.0 days
- Activity this month
- 5.0 days
- Activity this year
- 42.0 days
- Activity to date
- 42.0 days
- Estimate to complete current year
- 18.0 days
- Estimate to complete future years
- 0.0 days