Report for October 2019

Report Date
October 2019

Achievements this Period

  • Project Planning phase completed 
  • System related documentation 
    • The System Design Specification (SDS) document has been completed 
    • The Technical Architecture Document (TAD) has commenced 
    • The Test Strategy document has commenced 
  • Build Phase 
    • Initial discussions have commenced with the supplier regarding Single Sign-On (SSO)
    • The software build has commenced 

Issues 

  • Whilst it is the intention for staff to use their UUN to access the system, it has been noted user accounts have been uploaded using their Staff Id.  Discussions are currently on-going to resolve this matter with the supplier

Next Steps

  • System related documentation
    • Review the System Design Specification (SDS) document with the Production team 
    • Review the Technical Architecture Document (TAD) with the Production team
    • Confirm the Test Strategy document with the project team 
  • Build Phase 
    • Complete software build
    • Complete Single Sign-On (SSO)
  • User Acceptance Testing 
    • Confirm test schedule with the supplier 
    • Commence User Acceptance testing 
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
58.0 days
Activity this month
11.8 days
Activity this year
17.7 days
Activity to date
17.7 days
Estimate to complete current year
37.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Cardinus SSO and Account Provisioning
Code
HAS007
Programme
Health & Safety (HAS)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Candice Schmid
Current Stage
Plan
Status
In Progress
Start Date
20-Sep-2019
Planning Date
18-Oct-2019
Delivery Date
14-Feb-2020
Close Date
28-Feb-2020
Overall Priority
Normal

Documentation