- Report Date
- September 2019
Achievements this Period
- Project formally approved and project code assigned
- Project Planning
- meeting held with the project sponsor and business lead to review the project brief and outline project plan
- Project estimations completed with regards to
- provisioning accounts
- SSO
Issues
Next Steps
- Complete project planning phase
- Confirm development schedule with the supplier
- Approved budget
- 50.0 days
- Activity this month
- 2.7 days
- Activity this year
- 6.9 days
- Activity to date
- 6.9 days
- Estimate to complete current year
- 48.0 days
- Estimate to complete future years
- 0.0 days