w/c 9th December 2019

  • Regular Data Feeds Document 
    • The document has been updated to address the points of clarification raised by Student Systems and re-circulated for approval 
  • Information Security review 
    • Meeting held with Information Security, with the following points noted 
      • The defined process to transfer the data to Cardinus is ok
      • The SSO process requires to be documented in the TAD then will be reviewed
  • Project Technical Meeting 
    • ​​​​​​​Meeting held and minutes circulated to the project team 
  • ​​​​​​​Database account set up on Dev

Project Info

Project
Cardinus SSO and Account Provisioning
Code
HAS007
Programme
Health & Safety (HAS)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Candice Schmid
Current Stage
Plan
Status
In Progress
Start Date
20-Sep-2019
Planning Date
18-Oct-2019
Delivery Date
14-Feb-2020
Close Date
28-Feb-2020
Overall Priority
Normal