w/c 16th September 2019

  • Project Initiation 
    • Prepared project start-up submission documentation.  Approved by Project Sponsor 
    • Request to commence project approved by WIS
  • Project Planning 
    • Prepared first draft of project brief, project plan and project estimate 
    • Discussed possible development resourcing with the Development Resource Manager 
  • Initial Contact with the Supplier 
    • costs for data feed and SSO provided
    • confirmed outline project timescales - commencing 14th October would be acceptable

Project Info

Project
Cardinus SSO and Account Provisioning
Code
HAS007
Programme
Health & Safety (HAS)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Candice Schmid
Current Stage
Plan
Status
In Progress
Start Date
20-Sep-2019
Planning Date
18-Oct-2019
Delivery Date
14-Feb-2020
Close Date
28-Feb-2020
Overall Priority
Normal