Cardinus SSO and Account Provisioning - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
December 2019 GREEN 58.0 days 42.0 days 18.0
Content
Status
In Progress
Current Stage
Plan
Start Date
Friday, 20 September 2019
Planning Date
Friday, 18 October 2019
Delivery Date
Friday, 14 February 2020
Close Date
Friday, 28 February 2020
Project information
Project Code
HAS007
Programme
Health & Safety (HAS)
Session
19/20
Organisational Unit
Corporate Services Group
Project Management Office (if relevant)
ISG PMO
Responsibility
Applications Development and Operations
Overall Priority
Normal