Report for September 2019
- Report Date
- September 2019
Achievements this Period
- Project Closure Report completed and Project Closure meeting held
- Project Closure agreed and approved at WIS on 27-Sep-2019
- Business as part of Closure provided evidence of their satisfaction of:
- A contract
- An implementation plan
- A completed Procurement checklist
Issues
-
None
Next Steps
- None
Milestones:
The following milestones were agreed post WIS 28-Aug-2019:
| Milestone | Due Date |
| Exit Point - No Supplier Chosen | 19-Jul-2019 |
| Solution Deployment / Go Live | Withdrawn |
| Project Closure | 20-Sep-2019 |
- Approved budget
- 284.0 days
- Activity this month
- 6.2 days
- Activity this year
- 6.2 days
- Activity to date
- 90.5 days
- Estimate to complete current year
- 5.0 days
- Estimate to complete future years
- 0.0 days