Project journal

Title Description Author Post date
January security patches released 15-Feb

Oracle release January security patches - 15-Feb

  • will be included with the Phase 2 TYE patching
Anne Mathison 15-Jan-2020
Security Patches and Phase 1 planned for 4-Feb-2020 - C2001-037

Security Patches and Phase 1 planned for Feb 4th - C2001-037

Approved at Go Cab on 21-Jan

Anne Mathison 09-Jan-2020
Oracle Security Patches released available from 15-Oct

Oracle Security Patches released available from 15-Oct

Anne Mathison 16-Oct-2019

Project Info

Project
HR and Payroll Annual Maintenance 19/20
Code
FIN132
Programme
Finance (FIN)
Management Office
ISG PMO
Project Manager
Anne Mathison
Project Sponsor
Craig Henderson
Current Stage
Execute
Status
In Progress
Start Date
01-Oct-2019
Planning Date
30-Nov-2019
Delivery Date
03-Mar-2020
Close Date
09-Jul-2020
Overall Priority
Normal