- Report Date
- September 2019
Achievements in Last Period:
- Change in budget was agreed with Finance and WIS. This unfortunately has seen an increase from 42 to 52 days.
- Change in delivery date was agreed with Finance and WIS. This has led to a move from the 9th October to 25th November.
Issues:
- Finance resource constraints and focus on higher prioritised project work means that User Acceptance Testing (UAT) has yet to be concluded.
Next Steps:
- Preparations for implementation.
- Approved budget
- 52.0 days
- Activity this month
- 1.5 days
- Activity this year
- 3.0 days
- Activity to date
- 40.0 days
- Estimate to complete current year
- 12.0 days
- Estimate to complete future years
- 0.0 days