Preparations have been made for project implementation.
Agreement reached across the project team on a go-live date of the 10th December.
Issues:
Go-CAB had approved of a go-live on the 12th December but due to non-availability of internal and 3rd party staff, the date has provisionally been revised.
Lack of resource due to strike action means that a final confirmation date for implementation will not be until the first week of December.
Next Steps:
Confirm deployment and then move to DSOR and project closure.