Report for December 2019
- Report Date
- December 2019
Report for December 2019 by Ken Miller
Achievements in Last Period:
Work Stream (A)
- End-to-end Dual run of VAT return via For:sight for last quarters VAT return successfully carried out.
- Progress of PoC phase of project through to sign off.
- Review meeting agreed that purchase of the live solution would be outside the scope of tis project.
Work Stream (B)
- Carry out review of post go live issues and review lesson's learned.
Issues:
- (A) There remains a small manual element to the MTD process which may make it non MTD compliant. In particular the figures for boxes 2 and 9 of the VAT return will need to be manually submitted with the assistance of the For:sight tool. This risk has raised with the UoE Tax Office and they have agreed that they are the owner of this risk.
Next Steps:
Work Stream (A)
- Project closure tasks including addressing outstanding jira's.
Work Stream (A & B)
- Project Closure
Milestones:
| Stage | Milestone | Due Date | Complete |
|---|---|---|---|
| Plan |
(Workstream A) Signed Letter of engagement |
20-March-2019 | Yes |
| Plan | Planning Complete (Project Brief) | 03-May-2019 | Yes |
| Analyse | (Workstream B) Business Analysis Complete | 07-June-2019 | Yes |
| Execute | (Workstream A) Completion of For:sight Proof of Concept phase | 27-Sept-2019 | Yes |
| Analyse | Re-Planning Post Compliance (Workstream B) Scoping | 19-July-2019 | Yes |
| Build | (Workstream B) Build Complete | 13-Sept-2019 | Yes |
| Accept | (Workstream B) Acceptance Testing Complete | 27-Sept-2019 | Yes |
| Deliver | (Workstream A) Purchase of Arkk, For:sight bridging software | 25-Oct-2019 | Withdrawn |
| Deliver | (Workstream B) Deploy to Live | 18-Oct-2019 | Yes |
| Close | Project Closure | 31-Oct-2019 | No |
- Approved budget
- 50.0 days
- Activity this month
- 1.6 days
- Activity this year
- 19.4 days
- Activity to date
- 48.2 days
- Estimate to complete current year
- 2.0 days
- Estimate to complete future years
- 0.0 days