Report for October 2019

Report Date
October 2019

Report for October 2019 by Ken Miller

Achievements in Last Period:

Work Stream (A)

  • Dual run of VAT return via For:sight for last quarters VAT return to be carried out.  
  • A number conference calls held between Finance and Arkk to identify issues and work towards resolution.  Target date of 31/10/2019 not achieved but good progress made.
  • The Tax Office have escalated the outstanding issues with Arkk with the hope for quick resolution.
  • Arkk confirmed the process to promote the For:sight instance from PoC to Live.

Work Stream (B)

  • Liaise with Finance regarding resolution of outstanding issues.
  • Release of final upgrade to DEV and TEST for UAT.
  • After sign off from Finance roll out of final release to Live.  Awaiting final confirmation that project updates now completed and signed off in Live.

Issues:

  • (A) It has been confirmed that we will require a new legal contact.  Joanne MacConnell will be replaced by Esther Duncan.  Joanne's last day is 4th Oct and Esther doesn't start until November so there will be a gap.  During this period any correspondence should go to legalservices@ed.ac.uk, and a colleague will pick this up.
  • (A) There remains a small manual element to the MTD process which may make it non MTD compliant.  This risk has raised with the UoE Tax Office and they have agreed that they are the owner of this risk.
  • (B) The release to Live did not progress as smoothly as had been expected with a couple of issues still outstanding.  A review meeting has been arranged to review the release issues to ensure lesson's are learnt. 

Next Steps:

Work Stream (A)

  • Dual run of VAT return via For:sight for last quarters VAT return to be carried out.  
  • Progress of PoC phase of project through to sign off.
  • DPIA to be addressed once UAT has been signed off.
  • Clarify issues F Eardley has raised regarding the Arkk SLA.

Work Stream (B)

  • Receive final sign off from Finance regarding upgrade.
  • Carry out review of post go live issues and record in lesson's learned log to ensure they do not happen again.

Milestones:

 

Stage Milestone Due Date Complete   
Plan

 (Workstream A) Signed Letter of engagement

20-March-2019  Yes
Plan  Planning Complete (Project Brief) 03-May-2019  Yes
Analyse     (Workstream B) Business Analysis Complete          07-June-2019  Yes
Execute  (Workstream A) Completion of For:sight Proof of Concept phase 27-Sept-2019  No
Analyse  Re-Planning Post Compliance (Workstream B) Scoping 19-July-2019  Yes
Build  (Workstream B) Build Complete 13-Sept-2019  Yes
Accept  (Workstream B) Acceptance Testing Complete 27-Sept-2019  Yes
Deliver  (Workstream A) Purchase of Arkk, For:sight bridging software 25-Oct-2019  No
Deliver  (Workstream B) Deploy to Live 18-Oct-2019  No
Close  Project Closure 31-Oct-2019  No

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Project amber due to the proof of concept phase missing the 31/10/2019 target date. Good headway has been made recently and it is hoped that the discrepancies within the generated VAT return will soon be eliminated.
Change Status
Time
Moderate
Cost
No Change
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
Yes
Escalated to
Business Lead
Change Commentary
Project amber due to the proof of concept phase missing the 31/10/2019 target date. Good headway has been made recently and it is hoped that the discrepancies within the generated VAT return will soon be eliminated.
Activity
Approved budget
50.0 days
Activity this month
3.9 days
Activity this year
13.8 days
Activity to date
42.6 days
Estimate to complete current year
7.1 days
Estimate to complete future years
0.0 days

Project Info

Project
Essential Finance System Compliance Updates and Document Revitalisation
Code
FIN126
Programme
Finance (FIN)
Management Office
ISG PMO
Project Manager
Ken Miller
Project Sponsor
Craig Henderson
Current Stage
Initiate
Status
In Progress
Project Classification
Run
Start Date
18-Mar-2019
Planning Date
12-Apr-2019
Delivery Date
10-Oct-2019
Close Date
31-Oct-2019
Overall Priority
Normal
Category
Compliance