Current project status Report Date RAG Budget Effort Completed Effort to complete December 2019 RED 50.0 days 48.2 days 2.0 Content Status In Progress Current Stage Initiate Start Date Monday, 18 March 2019 Planning Date Friday, 12 April 2019 Delivery Date Thursday, 10 October 2019 Close Date Thursday, 31 October 2019 Project information Project Code FIN126 Programme Finance (FIN) Session 19/20 18/19 Organisational Unit Corporate Services Group Project Management Office (if relevant) ISG PMO Responsibility Applications Development and Operations Project Category Compliance Project Classification Run Overall Priority Normal