Report for May 2017
- Report Date
- May 2017
Achievements this period
WP2
- All minor bug fixes completed and tested
- UAT completed
- WP2 code / fixes deployed to live
- Draft completion report completed, for Project Team review 08/06/2017
Risks/Issues
WP2
- None
Next Steps
WP2
- Update TAD
- Complete Project (expected 09/06/2017)
Milestones
Acceptance (ASOR WP2) Sign Off - 28-APR-2017
Deploy WP2 - 15-MAY-2017
DSOR WP1/WP2 - 26-MAY-2017
CLOSURE - 02-JUN-2017
- Approved budget
- 170.0 days
- Activity this month
- 13.5 days
- Activity this year
- 159.3 days
- Activity to date
- 159.3 days
- Estimate to complete current year
- 8.9 days
- Estimate to complete future years
- 0.0 days