Monthly Progress for January 16

Report Date
January 2016

Achievements in last period:

  • Initiation of project
  • Project manager assigned
  • Project website set up

Issues:

  • None

Next Steps:

  • Estimation of project agreed
  • Discussion with Senior User
  • Draft Brief completed
  • Agree JAMS milestones and budget
  • Agree eTime milestones and budget
  • Brief approved
  • Established contact with supplier

Milestones:

Milestone DateMilestone Stage
12-Feb-2016Planning - Brief
29-Apr-2016JAMS Delivery Date
11-May-2016eTime Delivery Date
31-May-2016Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
50.0 days
Activity this month
1.9 days
Activity this year
1.9 days
Activity to date
1.9 days
Estimate to complete current year
57.4 days
Estimate to complete future years
0.0 days

Project Info

Project
Migrate eTime & JAMS applications
Code
FIN113
Programme
Finance (FIN)
Project Manager
Anne Mathison
Project Sponsor
Lee Hamill
Current Stage
Close
Status
Closed
Start Date
13-Jan-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
04-Jul-2016
Overall Priority
Normal
Category
Compliance