Monthly Progress for January 16
- Report Date
- January 2016
Achievements in last period:
- Initiation of project
- Project manager assigned
- Project website set up
Issues:
- None
Next Steps:
- Estimation of project agreed
- Discussion with Senior User
- Draft Brief completed
- Agree JAMS milestones and budget
- Agree eTime milestones and budget
- Brief approved
- Established contact with supplier
Milestones:
| Milestone Date | Milestone Stage |
| 12-Feb-2016 | Planning - Brief |
| 29-Apr-2016 | JAMS Delivery Date |
| 11-May-2016 | eTime Delivery Date |
| 31-May-2016 | Closure |
- Approved budget
- 50.0 days
- Activity this month
- 1.9 days
- Activity this year
- 1.9 days
- Activity to date
- 1.9 days
- Estimate to complete current year
- 57.4 days
- Estimate to complete future years
- 0.0 days