Report for June 2016

Report Date
June 2016

Achievements this period

  • Deployment Sign-Off confirmed for all applications by Project Team
  • Circulated project closure report for review and sign-off

Issues

  • None noted

Next steps

  • Close project
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
172.0 days
Activity this month
7.3 days
Activity this year
177.0 days
Activity to date
177.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days