Report for July 2016
- Report Date
- July 2016
Achievements in last period
- eFin password change deployed to Live (FIN109-8).
- Deployment sign-off confirmed.
- Closure sign-off confirmed.
- Project closed.
Issues
- n/a
Next Steps
- n/a
Milestones
Target date | Title | Complete |
---|---|---|
30-Sep-2015 | Brief approved | Yes |
11-Mar-2016 | Checkpoint: Decide whether to Un-suspend project | Yes |
18-Jul-2016 | Delivery of final enhancements batch | Yes |
22-Jul-2016 | Deployment Sign-off Review of final enhancements batch | Yes |
22-Jul-2016 | Closure Sign-off Review | Yes |
- Approved budget
- 40.0 days
- Activity this month
- 6.0 days
- Activity this year
- 40.0 days
- Activity to date
- 40.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days