Report for July 2016

Report Date
July 2016

Achievements in last period

  • eFin password change deployed to Live (FIN109-8).
  • Deployment sign-off confirmed.
  • Closure sign-off confirmed.
  • Project closed.

Issues

  • n/a

Next Steps

  • n/a

Milestones

Target dateTitleComplete
30-Sep-2015Brief approvedYes
11-Mar-2016Checkpoint: Decide whether to Un-suspend projectYes
18-Jul-2016Delivery of final enhancements batchYes
22-Jul-2016Deployment Sign-off Review of final enhancements batchYes
22-Jul-2016Closure Sign-off ReviewYes
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Activity
Approved budget
40.0 days
Activity this month
6.0 days
Activity this year
40.0 days
Activity to date
40.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
SAS Essential Enhancements
Code
FIN109
Programme
Finance (FIN)
Project Manager
Jill Nicoll
Project Sponsor
Lee Hamill
Current Stage
Close
Status
Closed
Start Date
16-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Jul-2016
Programme Priority
2
Overall Priority
Normal
Category
Discretionary