Report for June 2016

Report Date
June 2016

Achievements in last period

  • eAuthorisations BI universe and reports deployed to Live (FIN109-10)
  • eFin password change applied in Test (FIN109-8). Testing signed-off 5/7/16

Issues

  • The project's budget is under strain because the actual effort required for the eFin password change work has been higher than estimated. 
    • With the agreement of the Business Lead and the Programme Manager, the project budget will be balanced by transferring some of the completed effort on the eAuthorisations universe and report to FIN112.

Next Steps

  • Apply eFin password changes to Live (FIN109-8)
  • Close project

 

Milestones

Target dateTitleComplete
30-Sep-2015Brief approvedYes
11-Mar-2016Checkpoint: Decide whether to Un-suspend projectYes
01-Jul-2016Delivery of final enhancements batchNo
15-Jul-2016Deployment Sign-off Review of final enhancements batchNo
22-Jul-2016Closure Sign-off ReviewNo
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
40.0 days
Activity this month
5.8 days
Activity this year
37.6 days
Activity to date
37.6 days
Estimate to complete current year
3.7 days
Estimate to complete future years
0.0 days

Project Info

Project
SAS Essential Enhancements
Code
FIN109
Programme
Finance (FIN)
Project Manager
Jill Nicoll
Project Sponsor
Lee Hamill
Current Stage
Close
Status
Closed
Start Date
16-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Jul-2016
Programme Priority
2
Overall Priority
Normal
Category
Discretionary