Report for May 2016
- Report Date
- May 2016
Achievements in last period
- eFin password change applied in Dev (FIN109-8)
- Acceptance testing sign-off achieved for eAuthorisations universe and reports (FIN109-10)
- eFin BI access changes signed off in Live (FIN109-19)
Issues
- UAT Testing on the eAuthorisations BI universe and reports extended beyond the planned sign-off and deployment date, and beyond the planned budget.
- With the agreement of the Business Lead and the Programme Manager, the IS effort for this extension was transferred to FIN112.
Next Steps
- Deploy eAuthorisations BI universe and reports to Live (FIN109-10)
- Apply eFin password changes to Test (FIN109-8)
Milestones
Target date | Title | Complete |
---|---|---|
30-Sep-2015 | Brief approved | Yes |
11-Mar-2016 | Checkpoint: Decide whether to Un-suspend project | Yes |
01-Jul-2016 | Delivery of final enhancements batch | No |
15-Jul-2016 | Deployment Sign-off Review of final enhancements batch | No |
22-Jul-2016 | Closure Sign-off Review | No |
- Approved budget
- 40.0 days
- Activity this month
- 5.0 days
- Activity this year
- 32.0 days
- Activity to date
- 32.0 days
- Estimate to complete current year
- 9.0 days
- Estimate to complete future years
- 0.0 days