Report for March 2016

Report Date
March 2016

Achievements in last period

  • Project unsuspended

 

Issues

  • The project will be unable to progress until requirements have been confirmed, raised as Jiras, and selected for inclusion in a development Batch.  To date, no Jiras have been raised.  The project's scope therefore remains unknown.  Consequently, the Scope and Overall RAG statuses are Red.

 

Next Steps

  • Business Lead to raise Jiras for confirmed Batch 1 requirements, and assign to PM.

 

 

Milestones

Target dateTitleComplete
30-Sep-2015Brief approvedYes
11-Mar-2016Checkpoint: Decide whether to Un-suspend projectYes
01-Jul-2016Delivery of final enhancements batchNo
15-Jul-2016Deployment Sign-off Review of final enhancements batchNo
22-Jul-2016Closure Sign-off ReviewNo
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
RED
Overall
RED
Change Status
Activity
Approved budget
40.0 days
Activity this month
2.0 days
Activity this year
6.0 days
Activity to date
6.0 days
Estimate to complete current year
34.0 days
Estimate to complete future years
0.0 days

Project Info

Project
SAS Essential Enhancements
Code
FIN109
Programme
Finance (FIN)
Project Manager
Jill Nicoll
Project Sponsor
Lee Hamill
Current Stage
Close
Status
Closed
Start Date
16-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Jul-2016
Programme Priority
2
Overall Priority
Normal
Category
Discretionary