Report for June 2016

Report Date
June 2016

Achievement this period

  • Write-up of summary & recommendations document completed & distributed for review.
  • Meeting booked with Project Sponsor for review/sign-off

Issues

  • None

Next steps

  • Project closure

 

Target dateTitle
15-Jul-2016Final analysis paper complete
29-Jul-2016Closure

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
10.0 days
Activity this month
1.0 day
Activity this year
9.0 days
Activity to date
9.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Project
Supporting Scan and Destroy Policy Using Serengeti
Code
FIN104
Programme
Finance (FIN)
Project Manager
Dawn Holmes
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
24-Feb-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
28-Jul-2016
Category
Discretionary

Documentation