Report for May 2016

Report Date
May 2016

Achievement this period

  • Analysis of 'as is' process is complete
  • Statistics compiled on Serengeti reliability

Issues

  • The analysis has been more complex than anticipated as the current processwas not well understood or documentated.  This has resulted in a need for an additional 4 days budget to complete the analysis summary.
  • Due to annual leave and resource conflicts from higher priority projects, the analysis sign-off and closure have been moved out by 2 weeks.
  • As a result of these two issues the project is being reported on AMBER

Next steps

  • Complete write-up of summary & recommendations document

 

Target dateTitle
01-Jul-2016End of analysis
15-Jul-2016Closure
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
6.0 days
Activity this month
2.0 days
Activity this year
8.0 days
Activity to date
8.0 days
Estimate to complete current year
2.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Supporting Scan and Destroy Policy Using Serengeti
Code
FIN104
Programme
Finance (FIN)
Project Manager
Dawn Holmes
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
24-Feb-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
28-Jul-2016
Category
Discretionary

Documentation