Report for March 2015

Report Date
March 2015

Achievements this period

  •  Agreement reached between the various projects making changes to eAuthorisations regarding application code ownership & deployment

Issues

  • Resource conflicts for Project Manager and developer have meant that little progress has been made this month

Next steps

  • Integration testing & sign-off of workpackage 1
  • UAT of workpackage 1

 

Target dateTitle
07-Apr-2015Build sign-off workpackage 1
14-Apr-2015Integration sign-off workpackage 1
27-Apr-2015UAT sign-off workpackage 1
01-May-2015Delivery of workpackage 1 (OpenAM integration)
15-May-2015Deployment sign-off workpackage 1
28-Jul-2015Closure

 

Project Status
RAG Status
Overall
AMBER
Change Status
Activity
Approved budget
57.0 days
Activity this month
2.4 days
Activity this year
20.6 days
Activity to date
20.6 days
Estimate to complete current year
36.3 days
Estimate to complete future years
0.0 days

Project Info

Project
Launchpad phase 3 (eAuthorisations)
Code
FIN103
Programme
Finance (FIN)
Project Manager
Jill Nicoll
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
26-Jan-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2015
Overall Priority
Normal
Category
Discretionary