Report for March 2015
- Report Date
- March 2015
Achievements this period
- Agreement reached between the various projects making changes to eAuthorisations regarding application code ownership & deployment
Issues
- Resource conflicts for Project Manager and developer have meant that little progress has been made this month
Next steps
- Integration testing & sign-off of workpackage 1
- UAT of workpackage 1
| Target date | Title |
|---|---|
| 07-Apr-2015 | Build sign-off workpackage 1 |
| 14-Apr-2015 | Integration sign-off workpackage 1 |
| 27-Apr-2015 | UAT sign-off workpackage 1 |
| 01-May-2015 | Delivery of workpackage 1 (OpenAM integration) |
| 15-May-2015 | Deployment sign-off workpackage 1 |
| 28-Jul-2015 | Closure |
- Approved budget
- 57.0 days
- Activity this month
- 2.4 days
- Activity this year
- 20.6 days
- Activity to date
- 20.6 days
- Estimate to complete current year
- 36.3 days
- Estimate to complete future years
- 0.0 days