Report for January 2015

Report Date
January 2015

Achievements this period

  • Project kick-off meeting with Project Sponsor
  • Project website set up and initial planning meeting held with Software Development
  • Draft design done for workpackage 1 (OpenAM link)

Issues

  • This project was brought forward as a software development resource became available, but it has now emerged that the RMAS project requires this resource and agreement is still to be reached on how best to accommodate both projects

Next steps

  • Completion and sign-off of Project Brief
  • Build of workpackage 1 

 

Target dateTitle
06-Mar-2015Planning sign-off
30-Jun-2015Delivery
31-Jul-2015Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
57.0 days
Activity this month
3.2 days
Activity this year
3.2 days
Activity to date
3.2 days
Estimate to complete current year
53.9 days
Estimate to complete future years
0.0 days

Project Info

Project
Launchpad phase 3 (eAuthorisations)
Code
FIN103
Programme
Finance (FIN)
Project Manager
Jill Nicoll
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
26-Jan-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2015
Overall Priority
Normal
Category
Discretionary