Report for March 2015
- Report Date
- March 2015
Achievements this period
- Draft Project Brief and associated documentation underway
- Resources secured
Issues
- The delays to the pilot launch under project FIN098 are delaying the start of this project
Next steps
- Project planning
- Project foundations
| Target date | Title |
|---|---|
| 17-Apr-2015 | End of planning |
| 01-May-2015 | End of foundations |
| 26-Jun-2015 | End of development iterations (final delivery) |
| 10-Jul-2015 | End of maintenance iteration |
| 24-Jul-2015 | Project closure |
- Approved budget
- 180.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 180.0 days
- Estimate to complete future years
- 0.0 days