Report for July 2014

Report Date
July 2014

Achievements this period

  • Software build and peer testing completed
  • Build sign-off review completed

Issues

  • Decision still needed on which suspense accounts to use and how to include these in the batch header.  Decision agreed to proceed with deploy to Test so that we can demonstrate where things will currently coded in eFInancials

Next steps

  • Deployment to Test environment
  • Integration testing
  • Agree a decision of account coding

 

 

Target dateTitle
22-Aug-2014Integration sign-off
12-Sep-2014Acceptance sign-off
19-Sep-2014Go-live
03-Oct-2014Deployment sign-off
17-Oct-2014Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
120.0 days
Activity this month
5.0 days
Activity this year
63.0 days
Activity to date
63.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
50.0 days

Project Info

Project
SAAS/SLC Fees Reconciliation
Code
FIN094
Programme
Finance (FIN)
Project Manager
Dawn Holmes
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
16-Jan-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Jul-2015
Programme Priority
2
Category
Compliance