Report for May 2014
- Report Date
- May 2014
Achievements this period
- Planning stage sign-off, including the formal approval of the Project Brief
- Solution design agreed on. This design is quite a simple approach and the budget will be re-estimated
- System design document (SDD) has been completed and walked through with key stakeholders from FIS and Registry
Issues
- None at present
Next steps
- Formal design sign-off
- Re-estimate budget
- Software build
| Target date | Title |
|---|---|
| 02-Jun-2014 | Analysis & Design sign-off |
| 30-Jul-2014 | Build sign-off |
| 22-Aug-2014 | Integration sign-off |
| 12-Sep-2014 | Acceptance sign-off |
| 19-Sep-2014 | Go-live |
| 03-Oct-2014 | Deployment sign-off |
| 17-Oct-2014 | Closure |
- Approved budget
- 150.0 days
- Activity this month
- 10.3 days
- Activity this year
- 34.4 days
- Activity to date
- 34.4 days
- Estimate to complete current year
- 45.8 days
- Estimate to complete future years
- 48.0 days