Report for July 2015 - draft

Report Date
July 2015

 Achievements this period

  • Issue with student fees payments for previous academic years resolved
  • Issue with transposed date in eFinancials resolved
  • FInal version of software deployed to Live
  • Project closure meeting held and Completion Report signed-off
  • Project closed

Issues

  • None

Next steps

  • n/a

 

Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
108.0 days
Activity this month
3.6 days
Activity this year
42.6 days
Activity to date
105.7 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
SAAS/SLC Fees Reconciliation
Code
FIN094
Programme
Finance (FIN)
Project Manager
Dawn Holmes
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
16-Jan-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Jul-2015
Programme Priority
2
Category
Compliance