Report for March 2015

Report Date
March 2015

Achievements this period

  • Changes requested by Accounts Payable to the 'our ref' data have been addressed and released to Finance for UAT
  • Additional UAT has been undertaken but the Test eFin refresh cleared out the test data before the end-to-end tests could be completed so these will have to be repeated 

Issues

  • Further delays to UAT sign-off & subsequent go-live
  • The refresh of Test eFIn data undertaken by the RMAS project has cleared out the test data previosly set-up.  Additional test data now needs to be set up

Next steps

  • UAT sign-off
  • Go-live

 

Target dateTitle
10-Apr-2015Integration/Acceptance sign-off
14-Apr-2015Go-live
28-Apr-2015Deployment sign-off
05-May-2015Closure

 

Project Status
RAG Status
Overall
AMBER
Change Status
Activity
Approved budget
108.0 days
Activity this month
3.8 days
Activity this year
25.5 days
Activity to date
88.6 days
Estimate to complete current year
16.7 days
Estimate to complete future years
0.0 days

Project Info

Project
SAAS/SLC Fees Reconciliation
Code
FIN094
Programme
Finance (FIN)
Project Manager
Dawn Holmes
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
16-Jan-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Jul-2015
Programme Priority
2
Category
Compliance