Report for March 2015
- Report Date
- March 2015
Achievements this period
- Changes requested by Accounts Payable to the 'our ref' data have been addressed and released to Finance for UAT
- Additional UAT has been undertaken but the Test eFin refresh cleared out the test data before the end-to-end tests could be completed so these will have to be repeated
Issues
- Further delays to UAT sign-off & subsequent go-live
- The refresh of Test eFIn data undertaken by the RMAS project has cleared out the test data previosly set-up. Additional test data now needs to be set up
Next steps
- UAT sign-off
- Go-live
| Target date | Title |
|---|---|
| 10-Apr-2015 | Integration/Acceptance sign-off |
| 14-Apr-2015 | Go-live |
| 28-Apr-2015 | Deployment sign-off |
| 05-May-2015 | Closure |
- Approved budget
- 108.0 days
- Activity this month
- 3.8 days
- Activity this year
- 25.5 days
- Activity to date
- 88.6 days
- Estimate to complete current year
- 16.7 days
- Estimate to complete future years
- 0.0 days