Report for January 2014

Report Date
January 2014

Achievements this period

  • Project initiation and initial scope-finding meetings held with Finance, Registry Finance, SACS and Income Section

Issues

  • None to date

Next steps

  • Production of Project Brief and sign-off of end of planning

 

 

Target dateTitle
28-Feb-2014End of planning
30-Sep-2014Delivery

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
200.0 days
Activity this month
2.6 days
Activity this year
2.6 days
Activity to date
2.6 days
Estimate to complete current year
147.8 days
Estimate to complete future years
50.0 days

Project Info

Project
SAAS/SLC Fees Reconciliation
Code
FIN094
Programme
Finance (FIN)
Project Manager
Dawn Holmes
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
16-Jan-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Jul-2015
Programme Priority
2
Category
Compliance