SAAS/SLC Fees Reconciliation - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2015 BLUE 108.0 days 105.7 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Thursday, 16 January 2014
Close Date
Thursday, 30 July 2015
Project information
Project Code
FIN094
Programme
Finance (FIN)
Session
14/15
Organisational Unit
Finance Department
Project Category
Compliance
Programme Priority
2