Report for August 2015
- Report Date
- August 2015
Achievements in last period
- Build sign-off confirmed
- System deployed to Test
- Integration sign-off confirmed
- Released for UAT testing
Issues
- The project plan assumes that the bookings in place for the System Designer/Developer will not be lost to Priority 1 projects.
- It is very unlikely that the Designer/Developer's project booking will be able to be extended, since she is scheduled to move on to Priority 1 projects.
Next Steps
- Confirm Acceptance sign-off
- Deploy to Live
Milestones
| Target date | Title | Complete |
|---|---|---|
| 23-May-2014 | End of Planning | Yes |
| 06-Jun-2014 | Business Requirements Signed Off | Yes |
| 10-Jun-2014 | System Design Complete | Yes |
| 20-Apr-2015 | Checkpoint to Unsuspend Project | Yes |
| 05-Aug-2015 | Build Complete | Yes |
| 14-Aug-2015 | Integration Test Signed Off | Yes |
| 14-Sep-2015 | Acceptance Sign Off | No |
| 17-Sep-2015 | Deliver | No |
| 02-Oct-2015 | Deployment Sign Off | No |
| 08-Oct-2015 | Project Close | No |
- Approved budget
- 90.0 days
- Activity this month
- 8.0 days
- Activity this year
- 8.0 days
- Activity to date
- 67.0 days
- Estimate to complete current year
- 23.0 days
- Estimate to complete future years
- 0.0 days