September Report

Report Date
September 2014

Achievements in last period

  • Meeting held with DDSR and FINANCE at end of August to review demonstrators for the Finance Directorate document folders on Serengeti, this being based on the previously scanned documentation by DDSR and attributes provided by FInance
  • It was confirmed by Finance that they would prefer the folder structure to be created in same format for both backlog and future scanned documentation - action to be completed by Finance to identify folder type and breakdown each folder into tabs
  • Finance attendees advised that they will require additional resource from FTP to assist with this exercise, however they committed to complete this exercise in 2 weeks but expected additional resource would be required due to other committments on this basis it was agreed for them to confirm progress by end of the 2 week period - 15th September
  • DDSR to be provided with sample files once tab exercise completed
  • Further attribute details provided by Finance for a further 3 folders which have now been added to sample files

 

Issues

  • PM on special leave until 15th September
  • Due to other workload committments / annual leave in Finance no progress has been made on completing the folder exercise this has been raised to the Business PM to establish when work can commence / complete. Update provided from Business PM, one of resource is now on long term leave.
  • Project milestones cannot be reviewed and agreed until confirmation of Finance activity has been advised, this is to be discussed with Programme Manager and Project Sponsor should project be 'suspended' for a short period to allow resource to return and undertake tab exercise before recommencing project

 

Next Steps

  • Commence / complete folder type exercise
  • Review and agree new milestones
  • Replan activity for document scanning with DDSR

 

The project status is currently AMBER/ RED due to no progress having been completed by Finance to identify folder types and no current / agreed milestones

Target dateTitle
TBCBusiness Analysis
TBCDeploy to Development
TBCDocument Scanning Activity Completed
TBCDeploy to Test
TBCDeploy to Live
TBCClosure

 

Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
AMBER
Overall
AMBER
Change Status
Activity
Approved budget
70.0 days
Activity this month
0.9 days
Activity this year
2.9 days
Activity to date
32.8 days
Estimate to complete current year
35.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Document Management for Finance
Code
FIN081
Programme
Finance (FIN)
Project Manager
Karen Stirling
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Withdrawn
Start Date
22-Jan-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Feb-2016
Overall Priority
Normal
Category
Discretionary