Weekly update w/c 22/04/13
- Outputs from last week's meeting with the sponsor have been written up and returned for confirmation and prioritisation
- Workpackage 6 (salary forecasting fix) was flagged as an immediate priority by the sponsor and so has been completed by Apps Mgmnt under the FIN079 budget
- UAT of workpackage 2 (eIT enhancements) is being held up by an issue which requires a developer to resolve