Weekly update w/c 21/01/13

  • survey results published on the project website
  • 'thank you' email drafted & sent to project sponsor for distribution to survey participants
  • The project will now be suspended until April because of the eFin upgrade
  • A kick-off meeting has been booked for April to agree on next steps

Project Info

Project
LEAN Review of Financial Systems
Code
FIN079
Programme
Finance (FIN)
Project Manager
Dawn Holmes
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
01-Mar-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Oct-2013
Programme Priority
3
Overall Priority
Normal
Category
Discretionary