Report for April 2013

Report Date
April 2013

Achievements this period

  • The re-pointing of the application to the new eFIn databases was completed this month
  • Integration testing has taken place although formal sign-off has not taken place as one issue was still being worked on
  • Test plans were reviewed
  • The application has been handed over to FIS for acceptance testing

Issues

  • Integration testing was delayed by pressure of support issues.  This in turn meant that the developer was not available to address the re-work as they were assigned to other projects.  Overall this resulted in a 2 week delay.
  • The WPM expert in FIS is leaving the University at the end of May so the project is under increasing pressure to complete before that date.

Next steps

  • Acceptance testing by FIS
  • Go-live has been provisionally planned for w/c 3rd June 

 

 

Target dateTitle
24-Apr-2013Integration
03-Jun-2013Acceptance
11-Jun-2013Go-live
19-Jun-2013Deployment sign-off
27-Jun-2013Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
121.0 days
Activity this month
9.9 days
Activity this year
100.0 days
Activity to date
120.1 days
Estimate to complete current year
9.8 days
Estimate to complete future years
0.0 days