Report for March 2013

Report Date
March 2013

Achievements this period

  • The Dev application passed peer testing and the build stage was signed-off on 5th March

Issues

  • The project was made aware that the new eFIn database was located on a new server, so additional work/complexity was encountered in repointing the Dev application which has delayed the progression to Test.  New milestone dates have now been set.

Next steps

  • Deploy to Test for integration/acceptance testing

 

 

Target dateTitle
08-Apr-2013Re-point to new eFin
24-Apr-2013Integration
03-Jun-2013Acceptance
11-Jun-2013Go-live
19-Jun-2013Deployment sign-off
27-Jun-2013Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
121.0 days
Activity this month
2.9 days
Activity this year
90.1 days
Activity to date
110.3 days
Estimate to complete current year
22.8 days
Estimate to complete future years
0.0 days