Report for February 2013

Report Date
February 2013

Achievements this period

  • Build work completed
  • Peer testing of build completed
  • Build milestone

Issues

  • Knock-on delays from peer testing, caused by impact of eFin upgrade and unavailability of Dev environment

Next steps

  • Complete move to new upgraded eFIn database
  • Integration testing

 

 

Target dateTitle
13-Mar-2013Re-point to new eFin
02-Apr-2013Integration
09-May-2013Acceptance
17-May-2013Go-live
27-May-2013Deployment sign-off
11-Jun-2013Closure

 

 

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
121.0 days
Activity this month
21.7 days
Activity this year
80.5 days
Activity to date
90.1 days
Estimate to complete current year
31.4 days
Estimate to complete future years
0.0 days