Report for January 2013

Report Date
January 2013

Achievements this period

  • Build work is almost complete and is on-schedule

Issues

  • Invalid files from WPM continue to be an issue, but good progress has been made by Matthew Bunn is resolving these and valid files should be received in time for UAT

Next steps

  • Complete and sign-off build.
  • Migrate the application to the Test environment in preparation for UAT in March.

 

 

Target dateTitle
27-Feb-2013Build
19-Mar-2013Integration
24-Apr-2013Acceptance
02-May-2013Go-live
10-May-2013Deployment sign-off
27-May-2013Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
121.0 days
Activity this month
21.7 days
Activity this year
70.0 days
Activity to date
90.1 days
Estimate to complete current year
41.9 days
Estimate to complete future years
0.0 days