Report for November 2012

Report Date
November 2012

Achievements last period

  • Development environment is set-up
  • Development of agreed areas of functionality is underway

Issues

  • Due to outstanding queries regarding the provision of journal files from within the University, the system design has not been formally signed off.  However, as this is only one element of the design, build work is underway on the agreed elements.
  • WPM are slow to respond to issues encountered with the journal files on the gateway

Next Steps

  • Continue build work
  • Clarify internal file sources so that design can be formally signed off

 

 

Target dateTitle
02-Oct-2012System Design
15-Jan-2013Build
01-Feb-2013Integration
12-Mar-2013Acceptance
20-Mar-2013Go-live
28-Mar-2013Deployment sign-off
12-Apr-2013Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
121.0 days
Activity this month
11.0 days
Activity this year
48.0 days
Activity to date
68.0 days
Estimate to complete current year
64.0 days
Estimate to complete future years
0.0 days