Report for September 2012

Report Date
September 2012

Achievements in Last Period

  •  System design document completed in comjunction with Finance representatives from FIS

Issues

  •  The design has taken longer than estimated due to the variety of file formats that the application is required to handle.  This can be offset against the reduction from a 2-phase to a 1-phase delivery (pending approval from Internal Audit)
  • The revised estimation is higher than previously anticipated due to the complex nature of the requirements and the number of unknowns with the WPM element of the interface
  • The technical design (TAD) is not yet complete due to outstanding information on the WPM gateway

Next Steps

  • Meet with Internal Audit (meeting date secured)
  • Design sign-off
  • Secure funding for build or reduce scope of design
  • Build

 

Target dateTitle
02-Oct-2012System Design
15-Jan-2013Build
01-Feb-2013Integration
12-Mar-2013Acceptance
20-Mar-2013Go-live
28-Mar-2013Deployment sign-off
12-Apr-2013Closure

 

Project Status
RAG Status
Overall
AMBER
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days