Report for September

Report Date
September 2013

Achievements in last period

  • Go-live for Accommodation Services delegate registration files 9th September
  • Deployment sign-off on 13th September
  • Closure review 4th October

Issues

  • None 

Next steps

  •  Formal closure of project and project websites

 

There are no remaining milestones for this project.

Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
158.0 days
Activity this month
11.2 days
Activity this year
17.8 days
Activity to date
170.4 days
Estimate to complete current year
0.2 days
Estimate to complete future years
0.0 days