Report for September
- Report Date
- September 2013
Achievements in last period
- Go-live for Accommodation Services delegate registration files 9th September
- Deployment sign-off on 13th September
- Closure review 4th October
Issues
- None
Next steps
- Formal closure of project and project websites
There are no remaining milestones for this project.
- Approved budget
- 158.0 days
- Activity this month
- 11.2 days
- Activity this year
- 17.8 days
- Activity to date
- 170.4 days
- Estimate to complete current year
- 0.2 days
- Estimate to complete future years
- 0.0 days