Report for June 2013

Report Date
June 2013

Achievements

  • Following successful interfacing of both WPM and manual files, UAT sign-off was agreed in mid-June and the new JAMS application was installed onto Live.  However, shortly before it was activated we were made aware of a previously unknown requirement for multiple vat codes for delegate registration files for Accommodation Services (AS). The requirement was clarified with AS and FIS and plans put in place to make the necessary changes. 

Issues

  • Previously unknown requirement for multiple vat codes for delegate registration files resulting in delays to timescales and increased budget.

Next Steps

  • Complete changes for delegate registration vat (for AS)and clearing CLINK table upon failure (for FIS).
  • UAT and sign-off of changes
  • Go-live

 

 

Target dateTitle
22-Jul-2013Go-live
26-Jul-2013Deployment sign-off
02-Aug-2013Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
142.0 days
Activity this month
15.1 days
Activity this year
117.8 days
Activity to date
135.3 days
Estimate to complete current year
6.9 days
Estimate to complete future years
0.0 days