Status Report for August 2012

Report Date
August 2012

Achievements in Last Period

  • The developer has started work on the design as planned

Issues

  • none

 

Next Steps

  • Sign-off the system design

 

 

Target dateTitle
12-Sep-2012System Design
29-Oct-2012Phase 1 build
09-Nov-2012Phase 1 integration
03-Dec-2012Phase 1 acceptance
10-Dec-2012Phase 1 deployment
21-Feb-2013Phase 2 delivery
01-Mar-2013Deployment sign-off
18-Mar-2013Closure

 

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
121.0 days
Activity this month
3.0 days
Activity this year
3.0 days
Activity to date
23.0 days
Estimate to complete current year
98.0 days
Estimate to complete future years
0.0 days