Weekly update w/c 25/03/13 |
Issues were encountered during the repointing of the Dev application to the new eFIn Dev database/server, this meant that the project did not progress as planned during the Project Manager's leave and the planned repointing milestone date was not met. The developer's impending leave will further delay this stage of the project. The project has now been re-baselined with the relevant resources and revised milestone dates agreed to deploy to the Test environment w/c 08/04/13 |
Dawn Holmes |
29-Mar-2013 |
|
Weekly update w/c 25/02/13 |
- Peer testing was significantly delayed by issues with the Dev environmnent resulting from the eFin upgrade project. The environment was frequently unavailable or inaccessible.
- Peer testing finally completed on Wednesday (a week behind schedule) with just two issues requiring re-work (both now completed & re-tested).
- Build documentation (SDD, build test plan etc) now complete.
- The application can now be re-pointed to the new eFin database and the build sign-off completed.
|
Dawn Holmes |
01-Mar-2013 |
|
Weekly update w/c 11/02/13 |
- Additional requirement raised by Finance for a variable vat code
- Build work and associated documentation are almost complete.
- Peer testing scheduled to start next week
- Invalid files still being received from WPM
|
Dawn Holmes |
15-Feb-2013 |
|
Weekly update w/c 21/01/11 |
- Catch up meeting held with business rep
- Update received from Matthew on issues with WPM interface - the cause has been traced to the originating systems within the University and the relevant system owners have been notified
- Build work is ongoing and on schedule
|
Dawn Holmes |
24-Jan-2013 |
|
Weekly update w/c 14/01/13 |
- Catch-up meeting held with business rep last week to re-start the project after the festive break
- Build work is ongoing and seems to be on-track
- The impact of the eFin upgrade project was discussed, but it was felt that the impact should be minimal if that project stays on track as we will be deploying to Test as they are finishing.
|
Dawn Holmes |
18-Jan-2013 |
|
Weekly update w/c 17/12/12 |
- Developer is on leave
- Finance reps have reviewed the sample JAMS user interface and given positive feedback
- Meeting held with FIN083 eFin upgrade project to determine how the projects should work alongside an another in the Dev/Test environments. FIN078 work on the Test infrastructure will be suspended for the meantime. This does not affect the development work which can continue as currently but the Dev environment will need to be repointed to the new Dev database early in 2013.
- The project will now stop for the festive break and will reconvene w/c 7th Jan wh
|
Dawn Holmes |
21-Dec-2012 |
|
Weekly update w/c 10/12/12 |
- Build work was ongoing this week, but the developer is now on leave until January.
- The web interface is almost complete, the url has been provided to the business representatives so that they can give early feedback
|
Dawn Holmes |
14-Dec-2012 |
|
Weekly update w/c 03/12/12 |
|
Dawn Holmes |
06-Dec-2012 |
|
Weekly update w/c 12/11/12 |
- The developer has been on leave this week so no build work has taken place
- Catch-up meeting held with Finance reps to clarify outstanding design queries: -
- FInance confirmed that MyEd channel not required
- Finance confirmed that journal money totals should be the total of all the debit values
- Finance confirmated that there is an ongoing issue with the journal files produced by the live WPM gateway
- Garry to chase up origins of manual files so that the drop-off zone set-up can be finalised
|
Dawn Holmes |
16-Nov-2012 |
|
Weekly update w/c 05/11/12 |
|
Dawn Holmes |
12-Nov-2012 |
|
Weekly update w/c 29/10/12 |
- Build work ongoing
- Catch-up meeting held with Finance and some of the outstanding design queries have been resolved, however, there is still concern over the missing information regarding where the non-WPM files are coming from. Finance are to supply this information as a matter of urgency.
|
Dawn Holmes |
02-Nov-2012 |
|
Weekly update w/c 22/10/12 |
- Last few elements of design still being clarified
- New project estimation undertaken - 147 days (versus approved budget of 121 days) - most likely is 125 days. This has been discussed with the Programme Manager is now checking the programme budget to see if the extra days can be made available.
- Resources secured for the revised build phase
- Build work underway
|
Dawn Holmes |
25-Oct-2012 |
|
Weekly update w/c 15/10/12 |
- Catch-up meeting held to agree actions to complete outstanding design items
- Project Sponsor de-scoped manual file uploads and finance code validation (further details in Issue Log)
- Developer on leave
|
Dawn Holmes |
18-Oct-2012 |
|
Weekly update w/c 08/10/12 |
- Design review meeting held with key stakeholders but there were still some items to be confirmed.
- Further updates are required to the TAD and there are some minor items to be confirmed for the SDS, including: -
- confirmation of file naming
- confirmation of CLINK field content from Finance
- recommendations from Internal Audit
- method of finance code validation
- Outstanding items must be complete by the time the developer returns from leave on 22nd October.
|
Dawn Holmes |
12-Oct-2012 |
|
Weekly update w/c 01/10/12 |
- meeting held with Internal Audit to review the overall design. In general the design was acceptable but Internal Audit will be making some further recommendations.
|
Dawn Holmes |
04-Oct-2012 |
|
Weekly update w/c 24/09/12 |
- Design work is almost complete, only a few outstanding queries with Finance to complete. Draft document has been circulated prior to review meeting next week.
- Re-estimation in progress
|
Dawn Holmes |
28-Sep-2012 |
|
Weekly update w/c 10/09/12 |
- Further design work has taken place this week. The design is proving to be more involved than originally anticipated and additional time will be needed to complete this. Project Manager to reschedule resources when Resource Manager back from leave next week.
- Outstanding questions regarding the design are still sitting with Finance, these are being chased up.
- Initial discussions between the Developer and Dev Tech have taken place, this will allow the technical documentation to be drawn up.
|
Dawn Holmes |
14-Sep-2012 |
|
Weekly update w/c 03/09/12 |
- Weekly catch-up held with FInance representatives
- Design work ongoing
- Resource for Technical Design not available until the later part of next week, so some elements of the system design will have to wait to be confirmed
|
Dawn Holmes |
07-Sep-2012 |
|
Weekly update w/c 27/08/12 |
- The developer has started work on the design
- 2-weekly review meetings have been booked in diaries
|
Dawn Holmes |
30-Aug-2012 |
|
Weekly update w/c 20/08/12 |
Project on hold waiting for developer to commence work on 27/08/12 |
Dawn Holmes |
24-Aug-2012 |