Weekly update w/c 10/06/13

  • Test WPM files & manual csv files successfully loaded into eFin & posted
  • One remaining Jira with the developer for an enhancement to the description in eFin, this should be ready for testing by Monday
  • Draft plan drawn up to go-live mid-late next week.  These are tight timescales but we're keen to get the application live before our key contact in FIS leaves at the end of the month.