Report for October 2018

Report Date
October 2018

This project is to be suspended due to lack of subject matter expertise.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
200.0 days
Activity this month
6.7 days
Activity this year
14.4 days
Activity to date
14.4 days
Estimate to complete current year
8.8 days
Estimate to complete future years
0.0 days

Project Info

Project
Estates Security System Integration
Code
ESTS119
Programme
Estates Operations Optimisation (EOO)
Management Office
ISG PMO
Project Manager
Derrick Matheson
Project Sponsor
David Brook
Current Stage
Plan
Status
Suspended
Project Classification
Transform
Start Date
03-Sep-2018
Planning Date
28-Sep-2018
Delivery Date
29-Mar-2019
Close Date
19-Apr-2019
Programme Priority
2
Overall Priority
Normal
Category
Discretionary