Current project status Report Date RAG Budget Effort Completed Effort to complete December 2019 GREEN 69.0 days 26.0 days 41.0 Content Status In Progress Current Stage Plan Start Date Monday, 2 September 2019 Planning Date Friday, 20 September 2019 Delivery Date Monday, 16 March 2020 Close Date Wednesday, 8 April 2020 Project information Project Code EST126 Programme Estates General Programme (EST) Session 19/20 Organisational Unit Estates & Buildings Project Management Office (if relevant) ISG PMO Responsibility Applications Development and Operations Project Category Compliance Project Classification Run Project Type Infrastructure Project Size Small Project Complexity Simple Funding Source Core Programme Priority 2 Overall Priority Normal