Report for September 2019

Report Date
September 2019

Achievements Last Period

  • Programme Manager reviewed Project Brief
  • Workshops undertaken with Project Team SME's to agree details associated with WP's, deliverables and delivery dates/timescales - additional workshops needed to complete this activity
  • PICCLE submitted to WIs for revised End of Planning milestone

 

Issues / Outstanding

  • Further delays in completing WP/Deliverables reviews due to resource 'buy-in' and diary challenges
  • Awaiting return of Estates Transformation Programme Manager from annual leave/sick leave for review of Project Brief, plan etc before obtaining full board approval

 

Next Steps

  • Project Brief review and approval 
  • End of Planning submission to WIS
  • Execution activities per agreed plan

 

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
RAG status 'Amber' for time, as revised End of Planning milestone required - submitted but not yet approved. RAG status 'Green' for scope and budget as not yet base lined. Still working with Project Team to reassess for End of Planning
Change Status
Time
Moderate
Overall
Moderate
Has formal escalation taken place?
No
Change Commentary
Change RAG status for time 'moderate' as PICCL required to change End of Planning milestone as Project Team still to complete review of WP's and Deliverables and agree ownership and effort. Other RAG elements N/A as project not yet base lined. To be reassessed at End of Planning.
Activity
Approved budget
74.0 days
Activity this month
8.4 days
Activity this year
13.3 days
Activity to date
13.4 days
Estimate to complete current year
62.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Estates CAFM Stabilisation
Code
EST123
Programme
Estates Operations Optimisation (EOO)
Management Office
ISG PMO
Project Manager
Helen Lobb
Project Sponsor
Grant Ferguson
Current Stage
Plan
Status
In Progress
Project Classification
Grow
Start Date
19-Jul-2019
Planning Date
18-Oct-2019
Delivery Date
06-Dec-2019
Close Date
20-Dec-2019
Programme Priority
3
Overall Priority
Normal
Category
Discretionary

Documentation

Not available.