Report for September 2019
- Report Date
- September 2019
Achievements Last Period
- Programme Manager reviewed Project Brief
- Workshops undertaken with Project Team SME's to agree details associated with WP's, deliverables and delivery dates/timescales - additional workshops needed to complete this activity
- PICCLE submitted to WIs for revised End of Planning milestone
Issues / Outstanding
- Further delays in completing WP/Deliverables reviews due to resource 'buy-in' and diary challenges
- Awaiting return of Estates Transformation Programme Manager from annual leave/sick leave for review of Project Brief, plan etc before obtaining full board approval
Next Steps
- Project Brief review and approval
- End of Planning submission to WIS
- Execution activities per agreed plan
- Approved budget
- 74.0 days
- Activity this month
- 8.4 days
- Activity this year
- 13.3 days
- Activity to date
- 13.4 days
- Estimate to complete current year
- 62.0 days
- Estimate to complete future years
- 0.0 days