Report for September 2018
- Report Date
- September 2018
Achievements Last Period
Limited activity has taken place due to focus on EST099 and extended scope re Security assets, plus other items of focus. (EBIS and P2P projects). Also the need to better understand the strategic and business objectives of the Programme and then the Project.
Limited early 'knowledge gathering/understanding' meetings have taken place.
Early draft of Project Brief still in progress
Issues
Demands of other projects and limited engagement/time with Mass
Next Steps
Work with BA and states to better understand and define project objectives/scope/approach. Complete Project Brief
Arrange initial Project Board meeting
- Approved budget
- 108.0 days
- Activity this month
- 3.4 days
- Activity this year
- 8.4 days
- Activity to date
- 12.1 days
- Estimate to complete current year
- 105.0 days
- Estimate to complete future years
- 0.0 days